Rural Electrification Programme of Govt Of India, on a large scale throughout the country, particularly in northern states where the availability of electricity to villages is low.
Under the Programme the existing network is being revamped (called Feeder Renovation Programme) in addition to new lines, which are being installed to the remotest villages
Solution
:
Bajaj Electricals Ltd is also participating in this campaign and have recently finalized a contract worth Rs. 8 Crores from Jaipur Vidyut Vitran Nigam Ltd
The objectives of the Programme are as under:
Provide reliable power supply to all
Reduce AT & C losses
Reduce burning rate of Distribution Transformers
Reduction of Peak Demand in AG season
24 Hours reliable supply to rural domestic household as per national policy.
The total expenditure under the above Programme in Rajasthan within the next three years will be Approx 3000 Crores.
The scope consists of:
Installation of single-phase transformers to feed domestic and non-domestic load in rural areas
Providing of 25 KVA distribution transformers with a distribution box attached to its body, having provision for installation of meters, MCBs and Capacitor
Laying of direct insulated service line to each agricultural consumer from distribution transformers
Replacement of LT over head lines by ABC cables
Replacement of existing obsolete service line of consumers by armoured PVC / XLP cables
Installation of push-fit meters by replacing the existing sluggish meters